CBP border-wall contractors drilled unauthorized wells in New Mexico groundwater basins, allegedly tampered with meters to hide water diverted
On August 26, 2026, New Mexico's Office of the State Engineer sued the United States and three border-wall contractors — Barnard Construction Company Inc., Wyatt Drilling Arizona LLC, and Cascade Drilling LP — alleging they drilled water wells without required state authorization in the Mimbres, Hachita, and Lower Rio Grande groundwater basins to supply border-wall construction, and tampered with a totalizing meter to conceal how much water was diverted. State Engineer Elizabeth K. Anderson said the state would seek double repayment for all illegally diverted groundwater. The suit follows earlier August 2026 reporting that the state had already threatened to revoke the contractors' drilling licenses over the same unauthorized wells.
Actors
- U.S. Customs and Border Protection (border-wall program)
- Barnard Construction Company Inc. (CBP border-wall prime contractor)
- Wyatt Drilling Arizona LLC (border-wall drilling subcontractor)
- Cascade Drilling LP (border-wall drilling subcontractor)
On August 26, 2026, New Mexico's Office of the State Engineer filed suit in the state's Sixth Judicial District Court against the United States and three federal border-wall contractors, alleging illegal well drilling and water-meter tampering in protected groundwater basins along the U.S.-Mexico border. The complaint names Barnard Construction Company Inc. of Bozeman, Montana — the prime contractor on U.S. Customs and Border Protection's border-wall project — along with subcontractors Wyatt Drilling Arizona LLC and Cascade Drilling LP, as well as the United States. It alleges the defendants drilled water wells at multiple sites in the Mimbres, Hachita, and Lower Rio Grande groundwater basins without the State Engineer authorization New Mexico law requires, and tampered with a totalizing meter that would otherwise measure and disclose how much water a well diverts.
State Engineer Elizabeth K. Anderson said the state's permit process exists to protect water-rights holders and that the state would not allow the federal government to evade those protections. The lawsuit seeks an injunction halting further drilling and pumping, proper plugging and abandonment of the unauthorized wells, an accounting of water taken, and double repayment for all illegally diverted groundwater. New Mexico draws more than half its water from underground aquifers, and ranchers along the border have said the unpermitted wells threaten their cattle's water supply.
The suit follows earlier reporting in early August 2026 that the State Engineer's office had already documented at least eight unauthorized wells at multiple sites and threatened to revoke the contractors' drilling licenses. U.S. Customs and Border Protection responded at the time by saying it had instructed the contractor to pause installation of new wells — a step that addressed only future drilling, not the wells already in place, according to a rancher who discovered a well on his property. CBP has described the roughly $47 billion border-wall expansion, which includes work within a federally controlled strip of land along the international boundary, as requiring water for road-building, cement-mixing, and dust control.
Why we recorded this
State groundwater permitting exists to protect water rights holders and finite aquifers from unmonitored withdrawal, and federal contractors executing a federal project are not exempt from a state's statutory permitting and reporting requirements. Here, border-wall contractors drilled wells in three protected New Mexico groundwater basins without the State Engineer authorization the law requires, and allegedly tampered with a meter designed to measure water use — the very mechanism that lets the state verify compliance. This archive records the evasion of a state's statutory oversight regime, not merely an unpermitted-drilling dispute, because concealing the meter reading defeats the reporting requirement the statute exists to enforce.
Sources
- New Mexico sues feds over water drilling for border wall — KOB 4 primary accessed August 27, 2026
- New Mexico sues feds, contractors over water wells drilled to aid border wall construction — Source New Mexico (via Yahoo News) primary accessed August 27, 2026
- As anger mounts, feds tell border wall contractors to stop drilling for water in New Mexico — WBUR / Here & Now investigative accessed August 27, 2026
See also
- DHS and CBP waived Rivers and Harbors Act levee-safety review to keep building the Big Bend border wall amid a flood-risk lawsuit
- CBP border-wall contractor bulldozed the 1,000-year-old Las Playas Intaglio, a Tohono O'odham sacred site, in Arizona
- White House used unvetted TeleMessage Signal clone for records after Signalgate; May 2025 hack exposed CBP staff data
- Sen. Alan Armstrong disclosed 700 stock trades two months past STOCK Act deadline
- DHS Secretary Mullin waived dozens of environmental and historic-preservation laws for border wall construction from Big Bend to Lake Amistad
Receive the daily digest by email