ProPublica investigation reveals Army paid General Dynamics $533 million under no-bid contract for Texas plant that produced zero usable shells
A ProPublica investigation published August 12, 2026 found that the U.S. Army paid General Dynamics $533 million under no-bid "undefinitized contracting action" awards for a Mesquite, Texas artillery-shell plant that never produced a single usable 155mm shell in the roughly two years since it opened in May 2024. Congress had suspended competitive-bidding safeguards for Ukraine-related weapons production in December 2022, and despite the plant's total production failure the Army imposed no penalties, continued making progress payments, and General Dynamics went on to receive $2.5 billion in new contract awards.
Part of: Trump Administration No-Bid and Irregular Contracts
Actors
- U.S. Army (Federal agency)
- General Dynamics (Ordnance and Tactical Systems)
On August 12, 2026, ProPublica published an investigation finding that the U.S. Army paid General Dynamics $533 million under no-bid contract awards for an artillery-shell plant in Mesquite, Texas that has never produced a single usable 155mm shell since it opened in May 2024. In December 2022, Congress granted the Department of Defense special authority to fund Ukraine-related weapons production without normal contracting safeguards, dropping competitive bidding requirements and easing restrictions on "undefinitized contracting actions" that let a contractor begin work before contract terms are finalized. The Army used that authority starting in November 2022 to award General Dynamics a series of no-bid contracts, eventually worth close to $600 million, to build three production lines using unproven flow-forming equipment from a Turkish subcontractor, Repkon, without requiring General Dynamics to first demonstrate the equipment could make shells meeting Army specifications.
The plant was plagued from its May 2024 opening by equipment fires, malfunctioning robots, structural failures in the buildings themselves, and shells that failed inspection, according to interviews with three dozen current and former General Dynamics, Army, Pentagon and White House officials and a Department of Defense inspector general report. The Army ordered work halted on two of the plant's three production lines in August 2025 after General Dynamics missed eight deadlines, but did not terminate the contract awards. In December 2025, the government paid General Dynamics $26.3 million in "progress payments" for the idled second and third production lines despite neither having ever produced a usable shell, the inspector general's report found. The Occupational Safety and Health Administration opened an investigation into hazardous smoke at the plant in October 2024 but issued no penalties.
General Dynamics executives repeatedly told investors the plant was performing as planned even as internal conditions showed systemic failure; CEO Phebe Novakovic said in July 2024 that "the first line is running and producing as we anticipated" when it was producing no usable shells, according to former plant workers. The Army imposed no financial penalty on General Dynamics or Repkon and has not recouped the $533 million spent. Since halting the two production lines, General Dynamics' Ordnance and Tactical Systems division has received $2.5 billion in new Pentagon contract awards, which the Army says covers unrelated production lines and defense requirements. A separate Department of Defense inspector general evaluation found that as of March 2026 the Mesquite facility still had not produced any of the metal projectile parts it was contracted to make, contributing to the Army falling well short of its goal of producing 100,000 155mm shells per month.
Why we recorded this
Competitive bidding exists so taxpayer money buys the best deal available, not favors for a favored contractor. Congress suspended that safeguard for Ukraine-related weapons spending, and the Army used the opening to award General Dynamics no-bid contracts for a plant that went on to produce zero usable artillery shells — then kept paying the company, imposed no penalty, and steered it $2.5 billion in new contracts anyway. This archive records government contracting stripped of competitive-bidding accountability, because a process where failure carries no cost is patronage, not procurement.
Sources
- Fiasco in the Factory: Taxpayers Funded a $533 Million Artillery Plant That Made Nothing — ProPublica investigative accessed August 13, 2026
- Defense watchdog finds new 155mm artillery plant failed to produce parts in 2 years since it was built, hindering production goals — CBS News investigative accessed August 13, 2026
See also
- ICE extended Amentum's no-bid $776M contract to keep Camp East Montana open through 2027
- HHS awarded a $150 million sole-source contract to a firm founded by Trump EPA/Interior appointees for migrant children's legal defense
- ICE published notice of plan to buy up to $20M in electric-shock compliance gloves via no-bid contract
- Orange County audit found health director dismissed conflict warnings, steered no-bid contracts to allies
- NOTUS investigation revealed Interior Department pressuring National Park Service to trade Yosemite land to a private developer
Receive the daily digest by email
One email each morning with every entry filed the day before. Free. No tracking, no ads. Unsubscribe anytime.
