Criminal charges revealed former Tulsa Public Schools bond director Hudgins directed a decade-long kickback scheme benefiting his own company

Oklahoma Attorney General Gentner Drummond and Tulsa County District Attorney Steve Kunzweiler charged former Tulsa Public Schools Executive Director of Bonds and Energy Management Charles Christopher Hudgins, along with contractors Thomas McKenna and Gayle Gwinup of Allied Engineering Group, on June 4, 2026 with conspiracy, embezzlement and kickback violations. Prosecutors alleged Hudgins directed the district to pay Allied Engineering more than $779,000 for roofing projects never performed, with Allied Engineering funneling most of that money to Hudgins' own architecture firm. A state audit released August 18, 2026 found the full scheme, which ran from 2015 to 2025, diverted $3.73 million in misspent bond and rebate funds, including more than $2.6 million paid directly to Hudgins' business.

  • Charles Christopher Hudgins (Former Tulsa Public Schools Executive Director of Bonds and Energy Management)
  • Thomas McKenna (Co-owner, Allied Engineering Group)
  • Gayle Gwinup (Co-owner, Allied Engineering Group)

On June 4, 2026, Oklahoma Attorney General Gentner Drummond and Tulsa County District Attorney Steve Kunzweiler filed 27 criminal counts of conspiracy, embezzlement and kickback violations against former Tulsa Public Schools Executive Director of Bonds and Energy Management Charles Christopher Hudgins and two contractors, Thomas McKenna and Gayle Gwinup, partners in Tulsa-based Allied Engineering Group. Prosecutors alleged that Hudgins, who controlled vendor selection and oversight for the district's voter-approved bond projects, directed the district to pay Allied Engineering more than $779,000 for roofing projects the company never performed. Allied Engineering then funneled roughly $736,000 of that money to M&G Consulting, Hudgins' own private architecture firm, for work Drummond said was also never performed. Drummond said at a news conference that Hudgins additionally ran his private business on district time using district resources, calling the scheme "not a mistake" and "not an oversight."

The charges followed a Tulsa Public Schools audit ordered in 2022 by Gov. Kevin Stitt after two TPS board members raised concerns, conducted by State Auditor and Inspector Cindy Byrd's office, which first flagged Hudgins' conflict of interest in a February 2025 report and referred the matter to the Attorney General. Hudgins had left the district in February 2025. Hudgins, McKenna and Gwinup were each charged in Tulsa County District Court with conspiracy to defraud a school district, multiple counts of embezzlement, and making or receiving kickbacks; all three have pleaded not guilty. Tulsa Public Schools Superintendent Ebony Johnson said the district cooperated with the investigation and had put new financial-oversight safeguards in place.

Updates

2026-08-18 — State audit raised the documented misspending total to $3.73 million [4]

State Auditor and Inspector Cindy Byrd released the final installment of her office's audit of Tulsa Public Schools, finding that the scheme Hudgins ran from 2015 to 2025 diverted $3.73 million in bond and rebate funds -- well above the $779,317 originally charged. Auditors found Allied Engineering paid more than $2.6 million of the district's money directly to Hudgins' personal business, and separately that Hudgins had authorized, without school board approval, a company co-owned by Gwinup and two Allied Engineering employees to process $2.2 million in district energy rebates, keeping 30% of the proceeds. The audit also found Allied Engineering had overbilled the district by at least $499,573 for engineering work. Byrd said the losses stemmed from the Tulsa Board of Education giving Hudgins years of unilateral control and "rubber stamping" his recommendations without reviewing contracts. Drummond said his office is reviewing the full audit and that additional charges "are on the table."

Public bond funds approved by voters exist to build and repair the schools voters funded, not to become an official's personal revenue stream. Tulsa Public Schools' former bond director Charles Hudgins was charged with directing years of roofing and rebate-processing contracts to a contractor that in turn paid over $2.6 million to his own private business, and a later state audit found the scheme diverted $3.73 million in bond and rebate funds in total. This archive records the case because it shows a public official converting the independent authority voters' trust gave him over tax dollars into a private income stream, with a school board that never reviewed his contracts to catch it.

  1. Drummond, Kunzweiler: Former Tulsa schools executive charged in scheme to defraud Tulsa Public SchoolsOklahoma Attorney General's Office primary accessed August 19, 2026
  2. 'Coordinated scheme to defraud': Former TPS admin Chris Hudgins among trio chargedNonDoc investigative accessed August 19, 2026
  3. Former Tulsa schools official, construction contractors charged with stealing school bond moneyOklahoma Voice investigative accessed August 19, 2026
  4. State audit finds $3.73 million in misspent Tulsa Public Schools bond fundsOklahoma Voice primary accessed August 19, 2026